UPDATE WCR 23 3/4 Reconstruction Project

UPDATE on WCR 23 3/4 Street Reconstruction

Our contractor will begin reconstruction of WCR 23 3/4 on April 15, 2024.  The project is anticipated to take 12 weeks to complete.  The project will consist of a new roadway with two 13' travel lanes and a 12' center turn lane.  Curb, gutter & sidewalk will be installed.  Along with street lighting and a storm drainage system.  Traffic will be down to one lane of traffic during the reconstruction project.  Traffic will be controlled by flaggers and temporary signal lights.  If you have questions, please contact Jon Rabas Streets Director for the Town of Milliken at 970-587-4331